Before assembling the formwork, measure the elevation level of the concrete floor at the assembly position.
The level measurement is based on T.B.M (temporary level base point).
The measurement records shall be archived and kept by the designated supervisor.
Product Introduction
Our advanced management model has played a key role in helping our Villa Aluminum Formwork System, Flat Tie Concrete Modular, Column formwork to capture our customer base and reach a wide range of markets. We take quality first and premium service as our tenet to fully meet the needs of users with better product quality, first-class service and the most reasonable price. We warmly welcome clientele from all around the environment coming above for a visit and establishing long lasting connection. The pursuit of excellence and the challenge of limits is our long-standing and unwavering philosophy.
Level measurement
1) Before assembling the formwork, measure the elevation level of the concrete floor at the assembly position.
2) The level measurement is based on T.B.M (temporary level base point).
3) The measurement records shall be archived and kept by the designated supervisor.
4) When measuring, drawing positive (+) or negative (-) on the floor to mark the measurement result is an effective method.
5) Where the elevation along the wall line exceeds the design elevation by 10mm, it should be turned to no more than 10mm. Where the wall line is lower than the reference point, plywood or wood should be used to fill the template to the required level. The corners and low places in the walls must be fully filled.
6) After the concrete is poured, the top of the starting board (K board) outside the flat mold needs to be measured horizontally. The levelness of the starting board (K board) on the outside of the flat mold will cause the structure to deviate from the center line, otherwise the template cannot maintain its sag.
7) In order to facilitate adjustment of the starting board (K board) outside the flat mold after pouring, a 26mm long hole is opened.
8) Same as the level measurement of concrete surface, the measurement records of the starting board (K board) on the periphery of the flat form shall also be archived by the designated supervisor. At the same time, deviation detection should be performed and recorded and archived
Pay off
1). The error of the wall template line should be controlled within 1mm, and a control line should be placed in parallel in the same direction 150mm from the outside of the template line.
2) The stake-out line should pass through the opening, external angle, etc. at least 150mm to facilitate the control of the correct position of the template before pouring.
3) The reference point and the stakeout point are very important, which directly affect the verticality of the wall, and it is strictly forbidden to move or damage them.


We adhere to the business philosophy of service bearing responsibility. We integrate Large Area Wall Building Construction H20 Timber Beam Concrete Formwork System industry resources to create a one-stop service platform. Through hard and unremitting efforts, we hope to become an enterprise with efficient management, high marketability, strong international operation capability, and advanced technology and talents in the world. We know that talent is the first resource, the foundation of enterprise development and competition.
Hot Tags: column construction formwork mold, China, suppliers, manufacturers, cheap, quotation, low price, in stock, Flat Tie formwork System, Long Pin for Drop Head, Pin and Wedge, Struture Decking Concrete Slab, Villa Aluminum Formwork, Flat Tie Building Construction formwork
You Might Also Like
- 
   Painted Steel Props for Slab Formwork Supporting 
- 
   Concrete Sandwich Wall Panel Tilting Table Formwork 
- 
   New Product 45# Steel Column Steel Formwork 
- 
   Lianggong Timber Beam Wooden Formwork Table Formwork... 
- 
   Formwork Tie Rod with High Tensile Strength 
- 
   Domino Peri Aluminum Frame Adjustable Concrete Form ... 